Network Diagram: Graphical Representation of Activities and Their Dependencies

A Network Diagram is a visual representation of a project's activities and the dependencies between them, often used in project management to schedule and organize tasks.

A Network Diagram is a graphical tool that depicts the activities involved in a project and the dependencies between these activities. It is commonly used in project management to visualize the sequence of tasks, identify critical paths, and aid in the scheduling and management of project timelines.

Key Components

Activities

Activities represent distinct tasks or operations that are required to complete the project. In a network diagram, activities are typically shown as nodes (usually rectangles or circles).

Dependencies

Dependencies show the relationships and order between activities. These are depicted as arrows or lines connecting the nodes. Dependencies indicate the sequence in which activities must be performed.

Nodes and Arrows

Nodes (typically rectangles or circles) represent the activities, while arrows represent the dependencies or precedence relationships between the activities.

Critical Path

The critical path is the longest path through the network diagram, representing the sequence of activities that determine the shortest time possible to complete the project. Any delay in activities on the critical path directly affects the project’s completion time.

Types of Network Diagrams

Activity on Node (AON)

In an AON diagram, nodes represent activities, and arrows show the dependencies between them. This type of network diagram is also known as the Precedence Diagramming Method (PDM).

Activity on Arrow (AOA)

In an AOA diagram, arrows represent activities, and nodes indicate the start or end of these activities. This type is less commonly used than AON and is sometimes referred to as the Arrow Diagramming Method (ADM).

Creating a Network Diagram

Steps to Create a Network Diagram

  • Identify Activities: List all activities required to complete the project.
  • Determine Dependencies: Establish the logical sequence between activities.
  • Draw Nodes and Arrows: Create nodes for activities and connect them with arrows based on dependencies.
  • Calculate Early and Late Start/Finish Times: Use these calculations to identify the critical path.
  • Review and Adjust: Continuously update and review the network diagram as the project progresses.

Examples

Example of AON Network Diagram

1[ A ] --> [ B ] --> [ C ]
2                  |
3                  v
4               [ D ]

In this simplified example, Activity B can only start after Activity A is completed, and both Activities B and C must be completed before Activity D begins.

Example of AOA Network Diagram

1( A ) -->o--> ( B ) -->o--> ( D )
2                   \                   /
3                    \-->o--> ( C )-->/

Here, Activity B and Activity C can start after Activity A is completed. Both must be done before proceeding to Activity D.

Historical Context

The concept of network diagrams has its origins in the project management field. Tools such as the Critical Path Method (CPM) and Program Evaluation and Review Technique (PERT) were developed in the 1950s to manage complex projects in industries like defense and construction.

Applicability

Network diagrams are essential tools in various industries such as construction, software development, event planning, and manufacturing. They help project managers:

  • Visualize project scope and timelines.
  • Identify and manage task dependencies.
  • Optimize project schedules.
  • Allocate resources efficiently.

FAQ

What is the primary purpose of a network diagram?

The primary purpose is to visually represent the sequence of project activities and their dependencies, aiding in efficient project scheduling and management.

How does a network diagram help in identifying the critical path?

By outlining all activities and dependencies, it allows project managers to calculate the longest path of dependent tasks that determine the project’s minimum completion time.

What are the main differences between AON and AOA diagrams?

AON diagrams show activities as nodes and dependencies as arrows, while AOA diagrams represent activities as arrows and milestones or event nodes as circles or other shapes.

References

  1. Project Management Institute. (2017). A Guide to the Project Management Body of Knowledge (PMBOK Guide).
  2. Kerzner, H. (2013). Project Management: A Systems Approach to Planning, Scheduling, and Controlling.

Summary

In conclusion, a network diagram is a vital project management tool that facilitates the visualization and organization of project activities and their dependencies. By understanding the types, components, and benefits of network diagrams, project managers can ensure better project planning and execution.